Figure 1-13.SE Preoperational Record, OPNAV 4790/52.
Projected known operational commitments,
including the number of flights, flight hours, and aircraft
use
Date of scheduled inspections
Schedule of preinspection meetings
Dates of scheduled receipts or transfers of
aircraft and type of work to be done on these aircraft
PME calibration requirements
Schedule of technical training
Forced removal item (high time, and so forth)
Technical directive compliance (TDC)
Current list of QA personnel (QAR, CDQAR,
CDI)
Schedule of personnel for ejection seat safety
checkout
Date of scheduled SE inspections
Schedule of nondestructive inspection (NDI)
requirements
The MMCO prepares and publishes the MMP for
the AMOs signature. The MMP is distributed by the
25th of the month prior to which it applies. For
example, the MMP for April is distributed by the 25th
of March. Maintenance supervisors within the activity,
plus the supporting AIMD/IMA and the station/ship
supply officer, know the contents of the MMP.
AIMD/IMA MONTHLY
MAINTENANCE PLAN
The MMP is published by the AIMD/IMA for use
by the production divisions. The AIMD/IMA officer
holds a monthly meeting. Representatives of the
maintenance and supply departments of all supported
1-25