2-68.
Which of the following organizational
components or personnel has responsibility
for quarterly audits of work center
libraries?
1.
Individual work centers
2.
Maintenance administration
3.
CTPL librarian
4.
Maintenance control
2-69.
Which of the following should be reviewed
during the work center quarterly audit?
1.
2.
Condition of publications
Proper handling of TDs
3.
Proper storage of classified
publications
4.
Each of the above
Power Plants and Airframes discover deficiencies in
technical publications while making changes and
using the publications
Figure 2-E
IN ANSWERING QUESTIONS 2-70 THROUGH
2-75, REFER TO FIGURE 2-E.
2-70.
During incorporation of a change to a
technical manual the power plants
supervisor informed you that a publication
has a technical information deficiencies that
could affect safety of flight. What program
governs the appropriate course of action?
1.
NAMDRP
2.
IMRL
3.
ICRL
4.
CTPL
2-71.
What format or form should be used to
report deficiencies in tactical publications?
1.
SALTS
2.
OPNAV Form 3710/6
3.
OPNAV Form 4790/66
4.
CAT 1 priority message
2-72.
What report should be used to report this
deficiency?
1.
QDR
2.
HMR
3.
TPDR
4.
EI
2-73.
What format or form should use to report
this deficiency?
1.
OPNAV Form 3710/6
2.
OPNAV Form 4790/66
3.
CAT 1 TPDR priority naval message
4.
SALTS
2-74.
Airframes has informed you that one of
their publications has incorrect part
numbers. What methods should be used to
report this deficiency?
1.
CAT 1 TPDR priority naval message
2.
Rapid action minor engineering
change
3.
OPNAV Form 3710/6
4.
CAT 2 TPDR
2-75.
After getting confirmation that the
deficiency report has been received, what
method, if any, should you use to correct
the erroneous information in a publication?
1.
Use whiteout or correction tape to
remove the incorrect information and
leave blank until receipt of a formal
change
2.
Type the correct information in the
margins opposite the affected text
3.
Pen-and-ink correction
4.
None
17