2. When satisfied that the work has been properly
completed, the workcenter supervisor crosses
off, with an X, the maintenance requirement. If
the maintenance is not completed, the
maintenance requirement is circled and
rescheduled. However, if material deficiencies
or casualties that are unrelated to the
maintenance requirement are discovered, the
maintenance requirement can be X'd off, but
the discrepancy must be reported to the
workcenter supervisor. PMS requirements
(other than daily checks) accomplished during
the prescribed week but not on the day
specified are considered completed on
schedule and X'd off.
3.
Each Monday morning, the division officer
compares the preceding week's Weekly PMS
Schedule with the Quarterly Schedule and
ensures that the Quarterly Schedule is properly
updated as follows:
a.
Scheduled
requirements
that
were
completed are X'd out.
b.
Scheduled requirements that were not
completed are circled.
c.
Situation requirements that occurred and
were completed are entered and X'd off.
d.
Requirements that were completed ahead
of schedule are circled, back scheduled and
X'd out.
4.
Each Monday morning, the division officer
reviews the current week's Weekly PMS
Schedule, ensures that it is properly made out
according to the Quarterly Schedule, and signs
and
dates
the
Weekly
Schedule
in
the
appropriate block.
REVIEW QUESTIONS
Q4.
What maintenance requirements do the cycle
schedules display?
Q5.
All superseded cycle schedules are retained
for how many months?
Q6.
How often is the quarterly schedule updated?
THE MAINTENANCE DATA SYSTEM
LEARNING
OBJECTIVES:
State
the
purpose of the Maintenance Data System and
describe the types of maintenance actions
reported on the following OPNAV forms:
4790/2K, 4790/CK, 4790/2P.
The Maintenance Data System is used to record
information
considered
necessary
for
workload
planning and coordination and to provide a data base
for evaluating and improving equipment installed in the
fleet. Much of the data collected by MDS returns to the
ship in the form of a material history known as the
Current Ship's Maintenance Project (CSMP).
Nearly all the reporting of maintenance actions
other than normal PMS actions is done on a single
multipurpose form, the Ship's Maintenance Action
Form, OPNAV 4790/2K. Personnel completing a
maintenance action fill out the appropriate sections of
the form and send it via the ship's data collection center
to an ADP (automatic data processing) facility to be
processed. The 4790/2K contain information on the
reporter's ship, workcenter, equipment worked on, and
initial symptoms observed. In other sections, space is
provided to record completion information, deferral of
the work for various reasons, remarks, and special
information for work requests. A space also exists for
recording time meter and counter readings where they
are required.
Normally, the following types of maintenance
actions will be reported on the 4790/2K: system or
equipment repairs or improvements; maintenance
actions that require the use of parts or materials
specifically requisitioned for the job; actions that
cannot be completed in the usual amount of time due to
the
ship's
operations;
requirements
for
outside
assistance, or unavailability of parts or material;
assistance received from nonreporting activities, such
as mobile technical training units (MOTUs) or
technical representatives; major work associated with
corrosion control and preservation of the ship; and
certain PMS actions listed in the 3-M Manual,
OPNAVINST 4790.4.
7-21