5. Remove the coupling ring (fig. 4-37) by loos-
ening it first with the gear wrench, then unscrewing the
coupling ring with the special tool.
6. After removing the coupling ring, screw the lifter
into the bowl top. When you turn in on the T-handle
jackscrew on top of the lifter, the bowl top will let loose
from the bowl shell. Using the chain hoist, lift the
bowl top off, being careful with the rubber ring. Re-
move the rubber bowl ring and lay it flat.
7. Remove the tubular shaft, top disk, paring disk,
and intermediate disks, with the chain hoist, using the
special tool provided. (See figure 4-38.)
8. If removal of the bowl is required, lift out the
bowl strainer. Remove the spindle cap nut and back out
Figure 4-38.Removing disk stack.
4-47